Wind power plant Zelengrad, Obrovac
Investor
Eko Energija d.o.o.
Category
Energy
As the main contractor, in the period from July 2013 to March 2014, together with several renowned Croatian companies in the field of energy (Dalekovod d.d., ABB d.o.o., Mar d.o.o., etc.), we carried out the construction of the Zelengrad wind power plant in Obrovac with a capacity of 42 MW. The project included the construction of wind turbine foundations, the construction of the 30/110 kV Zelengrad substation, the 9.6 km long 110 kV transmission line, the construction of the MV cable layout of the wind farm, the supply and installation of electrical equipment, and the construction of access roads and paths.