Plant for compression and dehydration of CO2 at CPS Molve III
Investor
STSI integralni tehnički servisi d.o.o.
Category
Energy
From July 2012 to March 2013, on the project of the construction of a plant for compression and dehydration of CO2 at CPS Molve III. construction and tradesman works were carried out for the construction of a new substation with a control centre and a new compressor hall, as well as arranged internal roads and the environment of the plant.