The newer concrete bridge was repaired and reconstructed. Renovation of the span structure was carried out by: cleaning the surface with a hydro-destruction system, installing repair mortar made on the construction site, and installing special concrete based on diabase aggregates, steel and propylene fibres, and additives in the pavement slab.